Neighborhood Bikeway Prioritization and Scoping Project

Map of all eleven Neighborhood Bikeway Projects

This project will prioritize the City’s eleven Neighborhood Bikeway projects identified in the City's Transportation System Plan, and develop conceptual designs and cost estimates for the top five projects. Developing these projects will support the City in more accurately planning, budgeting and speeding up implementation of the next five Neighborhood Bikeway projects as these will be the projects included in the five-year Capital Improvement Program.

Project Timeline

March/April 2026: Public Open House (In-person & virtual) for Prioritization

July 2026: 30% Design

August 2026: Public Open House (In-person & virtual) for Conceptual Design

September 2026: Final Concept Design

Fall 2026: Final Scoping Study


Neighborhood Bikeway Prioritization Open House

The City of Corvallis conducted a public open house on March 31st, 2026 with City of Corvallis Public Works staff on hand to discuss the prioritization of the remaining eleven Neighborhood Bikeway projects.

City staff also conducted an online open house from March 31st through April 14th. The deadline to participate has concluded.

Though the time for initial input has closed, you may still view the presentation boards available from both open houses.


For more information, contact: 

Public Works at 541-766-6916 or ActiveTransportation@corvallisoregon.gov

Sign up for email updates (select 'Neighborhood Bikeways' from the list under 'News')